ST: 4.6.3. Interpret Cp and Cpk

Revision Date: 2005-09-07

The Cp and Cpk indices are the primary capability indices. Cp shows whether the distribution can potentially fit inside the specification, while Cpk shows whether the overall average is centrally located. If the overall average is in the center of the specification, the Cp and Cpk values will be the same. If the Cp and Cpk values are different, the overall average is not centrally located. The larger the difference in the values, the more offset the overall average. This concept is shown graphically below.

Cpk can never exceed Cp, so Cp can be seen as the potential Cpk if the overall average is centrally set. In the example, Cp is 1.17 and Cpk is 0.67. This shows that the distribution can potentially fit within the specification. However, the overall average is currently off center. The Cpk value does not state whether the overall average is offset on the upper or lower side. It is necessary to go to the Z values to discern this. An alternative is to show the capability indices Cpu and Cpl.

Previous    Next


The above article is an excerpt of the "Capability Analysis" section of Practical Tools for Continuous Improvement Volume 1 Statistical Tools.

Attachments Attachments
There are no attachments for this article.
Related Articles RSS Feed
ST: 1 What is it
Viewed 2528 times since Fri, Nov 9, 2007
ST: 4.4. Draw the specification limits on the distribution
Viewed 2182 times since Fri, Nov 9, 2007
ST: 4.2. Calculate the estimated standard deviation
Viewed 2825 times since Fri, Nov 9, 2007
ST: 4 How is it made
Viewed 2248 times since Fri, Nov 9, 2007
ST: 4.5.3. Determining the total percentage outside the specifications
Viewed 2471 times since Fri, Nov 9, 2007
ST: 4.6.2. Calculate Cpk
Viewed 10586 times since Fri, Nov 9, 2007
ST: 4.3. Determine the location of the tails for the distribution
Viewed 2146 times since Fri, Nov 9, 2007
ST: 4.5.2. Find the percentage below the lower specification
Viewed 2120 times since Fri, Nov 9, 2007
ST: 4.6.4. Calculate Cpu and Cpl
Viewed 8391 times since Wed, Nov 14, 2007
ST: 4.5. Calculate how much data is outside the specifications
Viewed 2426 times since Fri, Nov 9, 2007