Home » Categories » Statistics » Capability » Capability Analysis (from Practical Tools for Continuous Improvement)

ST: 4.7. Analyze the Results

Revision Date: 2005-09-07

The completed analysis for the example is shown below.

Calculations:

  = 2.00

 

Zupper = 2.00

Zlower = 5.00

Cpk = 0.67

Cp = 1.17

Cpu = 0.67

Cpl = 1.67

 

Examine the capability indices and the distribution. What do they show? Is the process capable? In the example, the process is off center, reflecting a capability issue. The upper specification of 14 minutes cannot be achieved consistently. The team must either improve the process or revise the specification. In the example, the team chose to revise the specification, but this is not an option in many industries.

The aim of capability is to achieve improved Cpk values, resulting in a more capable system. For most industries, the aim is to achieve a Cpk of at least one. Certainly this is the case for most service organizations. Some manufacturing companies require Cpk values greater than one. For example, the minimum is frequently 1.33, providing room for process drift, etc. When parts are being assembled, reduced variation at the center of the specification gives considerable benefit, namely parts assemble more quickly and more easily. Motorola, for example, constantly strives for higher and higher Cpk values. The company’s 6-sigma program has received a great deal of attention, and translates to a Cpk of 2.0. By pushing for improved Cpk values, the improvement effort is focused on shrinking variation around the center of the specifications.

Caution.

If a process is unstable—that is, if special causes are evident in the control chart—capability analysis will be unreliable. Every time the capability indices are calculated, they will be different. Special causes should be removed from a process. While special causes are present, the process is unpredictable, causing it to go in and out of specification. As soon as a special cause occurs, the Cpk is meaningless, since special causes often result in unpredictable defects; even an apparently good Cpk can not be relied upon.

If the sampling selected in the control chart is not appropriate for the process, this can also affect the Cp/Cpk values. For example, sampling too frequently will artificially reduce the range values and cause the Cp/Cpk values to appear high. Using the wrong sample size can have a similar effect. Refer to the sampling section for guidance with appropriate sample size and frequency.

If the data being analyzed is not normal, the estimated standard deviation () will not be accurate. Nonnormal capability analysis must be used if the distribution is not normal, refer to the topic "Nonnormal capability analysis," later in this section for more information. The method shown in this section can be significantly affected by nonnormal data, giving inaccurate results.


The above article is an excerpt of the "Capability Analysis" section of Practical Tools for Continuous Improvement Volume 1 Statistical Tools.

Attachments Attachments
There are no attachments for this article.
Related Articles RSS Feed
ST: 4.6. Calculate and interpret the capability indices
Viewed 3520 times since Mon, Dec 10, 2007
ST: 4.5.3. Determining the total percentage outside the specifications
Viewed 2454 times since Fri, Nov 9, 2007
ST: 4.2. Calculate the estimated standard deviation
Viewed 2803 times since Fri, Nov 9, 2007
ST: 4.5.1. Find the percentage above the upper specification
Viewed 2130 times since Fri, Nov 9, 2007
ST: 1 What is it
Viewed 2507 times since Fri, Nov 9, 2007
ST: 4.6.2. Calculate Cpk
Viewed 10549 times since Fri, Nov 9, 2007
ST: 3 When is it used
Viewed 2183 times since Fri, Nov 9, 2007
ST: 4 How is it made
Viewed 2229 times since Fri, Nov 9, 2007
ST: 4.6.3. Interpret Cp and Cpk
Viewed 11265 times since Thu, Jan 10, 2008
ST: 4.5.2. Find the percentage below the lower specification
Viewed 2096 times since Fri, Nov 9, 2007